General Electric to Increase Efficiency of EPS’ Coal-Fired Power Plant

More...

G20 Summit: G20 Leaders United To Address Major Global Pandemic And Economic Challenges

President of the European Commission, Ursula von der...

SSCC promotes the Serbian ICT market to Swiss companies

SSCC promotes the Serbian ICT market to...

Government Of Serbia Adopts 2021 Budget Bill

At today's session, the government of the...

EU Donates Ambulances, Mobile Respirators And Protective Equipment

Twelve new ambulances with modern equipment, decontamination...

News

G20 Summit: G20 Leaders United To Address Major Global Pandemic And Economic Challenges

President of the European Commission, Ursula von der Leyen, and President of the European Council, Charles Michel, represented the EU at...

SSCC promotes the Serbian ICT market to Swiss companies

SSCC promotes the Serbian ICT market to Swiss companies in cooperation with Switzerland Global Enterprise. Switzerland Global Enterprise S-GE...

Government Of Serbia Adopts 2021 Budget Bill

At today's session, the government of the Republic of Serbia adopted the Bill on the Budget of the Republic...

EU Donates Ambulances, Mobile Respirators And Protective Equipment

Twelve new ambulances with modern equipment, decontamination vehicles and protective equipment will be available to the health system in...

Government Passes New Anti-coronavirus Measures

The Serbian government adopted new measures to suppress the epidemic caused by the COVID-19 infectious disease, whose implementation will...

General Electric’s Power Services announced that this year it will complete the modernization of Elektro Privreda Srbije’s (EPS) TPP Nikola Tesla, the largest coal-fired power plant in Serbia. GE’s steam turbine retrofit will help increase power output, reduce operational and maintenance costs and lower plant carbon footprint through less coal consumption.

“EPS’ TPP Nikola Tesla power plant provides a large portion of the power supply for the Serbian electricity system,” said Savo Bezmarevic, EPS production executive, Elektroprivreda Srbije JP. “We need our assets to operate at the highest availability, efficiency and reliability levels as possible, as it is crucial for Serbia to have a secure energy supply.”

The power plant features two, 210-megawatt (MW) LMZ steam turbines and four (A3-A6), 308-MW GE units. GE will provide a steam turbine full shaft line retrofit solution for high-pressure, intermediate-pressure and low-pressure turbine modules as well as a new turbine governing controller system. In addition to the controller, the project includes GE’s advanced 3-D blades, new rotors, rotary blades, stationary blades, inner and outer casings and other associated parts.

As part of the agreement, GE will commission a WT23S-106 generator unit—the largest ever installed in Serbia—at the TPP Nikola Tesla B2 site to help improve availability and reliability of the plant.

“EPS will continue with modernizations and revitalizations to secure a stable power supply, which is in line with the government’s strategy to bring a more modern and efficient electric power system to Serbia,” said Milorad Grcic, general manager, Elektroprivreda Srbije JP. “The steam turbine retrofit will give a new life cycle after 250,000 operating hours and increase power output by 24 MW.”

The operating life of the steam turbine unit—an estimated 250,000 working hours—will be extended for an additional 100,000 operating hours, and the maintenance intervals between major overhauls will be extended to nearly 10 years.

The steam turbine retrofit is expected to start in May 2017, and the commissioning of the upgraded equipment is scheduled for October 2017.

“A recent GE analysis found that carbon dioxide emissions from the world’s fleet of coal and gas plants can be reduced by 10 per cent when existing hardware and software solutions are fully applied,” said Pascal Schweitzer, general manager, GE’s Power Services in Europe.

“We are proud to build on our long relationship with Elektroprivreda Srbije JP to provide them with new technology solutions to help them generate more efficient and cleaner power aligned with Serbian environmental targets.”

Related Articles

Serbia’s EPS Net Profit Rises In H1

State-owned power utility Elektroprivreda Srbije (EPS) said its net profit more than doubled to 7.898 billion dinars ($78.8 million/67.2 million euro) in the first...

EPS - Always With Serbia's Citizens and Economy

Enough Energy, Continued Investment

The energy system worked reliably throughout the epidemic, thanks to the extra efforts of the employees of Elektroprivreda Srbije . During this time of...

EPS Improves Capacities

EPS Investments in Modern Energy

The major investment cycle of electric utility power company EPS (Electric Power Industry of Serbia) is continuing with increasing intensity throughout Serbia, with the...

Siemens and CMEC sign a contract on Fire Protection System in Kostolac Thermal Power Plant

China Machinery Engineering Corporation (CMEC) and Siemens Belgrade signed today a contract on design, procurement and provision of services for the Fire Protection System...

EPS begins sale of green energy

The state company Elektroprivreda Srbije (EPS) began selling green energy to commercial customers, and the first major buyer in Serbia with whom the contract...

Elektroprivreda Srbije

EPS – On The Green Road

The need to advance environmental protection, Serbia’s moving closer to the European Union, and electricity market opening are the main reasons why EPS is...

Results Show EPS’s Strength

EPS Day Marked on 6th October

Pavilion Serbia At Expo Astana 2017

This occasion saw the National Day of Serbia celebrated with a full-day programme in Astana